Koper town marina

Next to the old mandracchio in Koper, we restored the dilapidated and partly demolished pier by casting encasing concrete on the existing stone wall, and we built a new 165 m long breakwater, thus giving the Koper town marina several new berths. To complete the project, we installed 215 piles of 15 m in length and set up 100 reinforced concrete elements to build the breakwater. We also dredged the sea-bed excavating 9,600 m3 of material. With the help of divers, we laid 500 m3 of underwater concrete to make the ground slab and 40,000 kg of rebars.

Delivery date: 2008
Project location: Koper
Final value of the project: EUR 1,240,000
Investor/Client: Municipality of Koper/Stavbenik