⊕ References / Marine Construction
Temporary mooring facility for the needs of the Slovenian Armed Forces
01 / PROJECT DESCRIPTION
About the project
Within the construction works, 6 piles were driven and reinforced concrete pile caps were installed on them. This was followed by the concreting of supporting beams, on which the structure of the access bridge was mounted. On the sea side, 8 pontoons with a total length of 78 meters were installed, ensuring a stable and safe connection between the shore and the vessels of the Slovenian Armed Forces.
Technical data
- 6 piles with reinforced concrete heads
- 8 pontoons with a total length of 78 m
- Reinforced concrete load-bearing beams with access bridge